1. |
A and B can do a piece of work in 12 days, B and C in 15 days, C and A in 20 days. How long would A take separately to do the same work? |
A. | 10 days |
B. | 20 days |
C. | 30 days |
D. | 40 days |
Answer» D. 40 days | |