A and B can do a piece of work in 12 days. B and C can do it in 15 days. A and C can do the same piece of work in 20 days. In how many days can A, B and C each finish the same work independently ? |
A. | 30 days, 20 days, 60 days |
B. | 40 days, 10 days, 30 days |
C. | 10 days, 30 days, 40 days |
D. | None of the above |
Answer» B. 40 days, 10 days, 30 days | |