A and B can do a piece of work in 8 days, B and C can do the same work in 12 days and A, B and C together can complete the same work in 6 days. Then find the required time in which A and C can complete the work together. |
A. | 12 days |
B. | 9 days |
C. | 6 days |
D. | 8 days |
Answer» E. | |