A and B can do a piece of work in 30 days, while B and C can do the same in 24 days and C and A in 20 days. They all work together till 12th day then A and C leave. How many more days will it be required for B to finish the remaining work?

A. 24 days
B. 22 days
C. 16 days
D. 20 days
Answer» E.