1.

A and B can complete a task together in 35 days. If A works alone and completes 5/7 of the task and then leaves the rest for B to complete by herself, it will take a total of 90 days to complete the task. How many days would it take A, the more efficient among the duo, to complete the entire work by herself?

A. 40
B. 45
C. 48
D. 42
Answer» E.