MCQOPTIONS
Saved Bookmarks
1. |
A and B can complete a task in 18 days. However, A had to leave a few days before the task was completed and hence it took 27 days in all to complete the task. If A alone could complete the work in 21 days, how many days before the work getting over did A leave? |
A. | 12.5 |
B. | 14 |
C. | 10.5 |
D. | 9 |
Answer» D. 9 | |