| 1. |
A and B can complete a task in 1.5 days. However, A had to leave a few days before the task wascompleted and hence it took 2 days in all to complete the task. If A alone could complete the work in2.625 days, how many days before the work getting over did A leave? |
| A. | 1.125 |
| B. | 0.625 |
| C. | 0.375 |
| D. | 0.875 |
| Answer» E. | |