| 1. |
A and B can complete a piece of task together in 12 days while A alone can do it in 15 days. They start working together but A leaves 10 days before the completion of the task. For how many days did A and B work together? |
| A. | 9 |
| B. | 10 |
| C. | 8 |
| D. | 11 |
| Answer» C. 8 | |