A and B can complete a piece of task together in 12 days, while A alone can do it in 15 days. They start working together but A leaves 10 days before the completion of the task. For how many days did A and B work together? |
A. | 10 |
B. | 11 |
C. | 8 |
D. | 9 |
Answer» B. 11 | |