‘A’ alone completes \({\frac{4}{5}^{th}}\) part of a work in 20 days. The remaining work then completed by A and B working together in 3 days. How long would ‘B’ alone take to do two times the original work?

A. \(37\frac{1}{2}\;days\)
B. 40 days
C. 75 days
D. 80 days
Answer» D. 80 days