A alone can do a work in 20 days. B is 125% more efficient than A. A and B started working and worked for 4 days. If C alone completed the remaining job in 22 days. How many days C alone takes to complete the entire job? |
| A. | 30 |
| B. | 35 |
| C. | 40 |
| D. | 42 |
| Answer» D. 42 | |