A alone can complete a work in 16 days and B alone in 12 days. Starting with A, they work on alternate days. The total work will be completed in: |
A. | 12 days |
B. | 13 days |
C. | 13 3/4 days |
D. | 13 5/7 days |
Answer» D. 13 5/7 days | |