1.

A alone can complete a work in 10 days and B alone can complete the same work in 20 days. In how many days both A and B together can complete half of the total work?

A. 40/3 days
B. 20/3 days
C. 10/3 days
D. 25/3 days
Answer» D. 25/3 days