1. |
90 men are engaged to do piece of work in 40 days but it is found that in 25 days, 2/3 work is complete. How many men should be allowed to go off, so that the work finished in time ? |
A. | 10 |
B. | 15 |
C. | 20 |
D. | 25 |
Answer» C. 20 | |