1. |
8 men can complete a work in 12 days, 4 women can complete it in 48 days and 10 children can complete the same work in 24 days. In how many days can 10 men, 4 women and 10 children complete the same work ? |
A. | 10 days |
B. | 5 days |
C. | 7 days |
D. | 6 days |