6 skilled workers can dig a pond in 8 days while it takes 9 unskilled workers 12 days to dig it. How many days will it take 4 skilled and 18 unskilled workers to dig such a pond? |
A. | 2 |
B. | 5 |
C. | 4 |
D. | 3 |
Answer» D. 3 | |