6 skilled workers can dig a pond in 8 days while it takes 9 unskilled workers 12 days to dig it. How many days will it take 4 skilled and 18 unskilled workers to dig such a pond?

A. 2
B. 5
C. 4
D. 3
Answer» D. 3