50 men or 80 women can finish a job in 50 days. A contractor deploys 40 men and 48 women for this work but after every duration of 10 days, 5 men and 8 women are removed till the work is completed. The work is completed in ?

A. 45 days
B. 50 days
C. 54 days
D. 62 days
Answer» C. 54 days