36 workmen are employed to finish a certain work in 48 days. But it is found that in 24 days only 2/5 work is done. How many more men must be employed to finish the work in this ? |
A. | 16 |
B. | 18 |
C. | 20 |
D. | 22 |
E. | None of the above |
Answer» C. 20 | |