35 persons are engaged to complete a work in 60 days. After 32 days it is observed that only (2/5)th part of the work has been done. The number of persons to be engaged to complete the remaining work in the said period is |
A. | 20 |
B. | 35 |
C. | 30 |
D. | 25 |
Answer» E. | |