32.A does 4/5 of the work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone take to finish the whole work? |
| A. | 37 ½ days |
| B. | 36 ½ days |
| C. | 35 ½ days |
| D. | 34 ½ days |
| Answer» B. 36 ½ days | |