1. |
30 men can complete a job in 40 days. However, after 24 days some men left the job. The remaining people took another 40 days to complete the job. The number of men who left the job is |
A. | 24 |
B. | 18 |
C. | 12 |
D. | 6 |
Answer» C. 12 | |