1.

 30 labourers working 7 hours a day can finish a piece of work in 18 days. If the labourers work 6 hours a day, then the number of labourers required to finish the same piece of work in 30 days will be

A. 13 days
B. 18 days
C. 21 days
D. 25 days
Answer» D. 25 days