3 men and 4 boys can complete a piece of work in 12 days. 4 men and 3 boys can do the same work in 10 days. Then 2 men and 3 boys can finish the work in number of days is |
A. | <table><tr><td rowspan="2">17</td><td style="border-bottom:1px solid #000000;vertical-align:bottom;padding-bottom:2px;"><center>1</center></td><td rowspan="2">days</td></tr><td align="center">2</td></table> |
B. | <table><tr><td rowspan="2">5</td><td style="border-bottom:1px solid #000000;vertical-align:bottom;padding-bottom:2px;"><center>5</center></td><td rowspan="2">days</td></tr><td align="center">11</td></table> |
C. | 8 days |
D. | 22 days |
Answer» B. <table><tr><td rowspan="2">5</td><td style="border-bottom:1px solid #000000;vertical-align:bottom;padding-bottom:2px;"><center>5</center></td><td rowspan="2">days</td></tr><td align="center">11</td></table> | |