1. |
25 men and 15 women can complete a piece of work in 12 days. All of them start working together and after working for 8 days the women stopped working. 25 men complete the remaining work in 6 days. how many days will it take for completing the entire job if only 15 women are put on the job ? |
A. | 60 days |
B. | 88 days |
C. | 94 days |
D. | None of these |