1. |
20 men can do a piece of work in 14 days working 8 hrs a day. How many men are needed to complete another work, which is twice the first one, in 8 days working 16 hrs a day? |
A. | 40 |
B. | 35 |
C. | 28 |
D. | 32 |
Answer» C. 28 | |