2 men and 1 woman can complete a piece of work in 14 days while 4 women and 2 men can do the same work in 8 days. If a man gets 60 per day, what should be the wages per day of a woman? |
A. | 30 |
B. | 35 |
C. | 40 |
D. | 50 |
Answer» D. 50 | |