1.

2 men and 1 woman can complete a piece of work in 14 days while 4 women and 2 men can do the same work in 8 days. If a man gets 60 per day, what should be the wages per day of a woman?

A. 30
B. 35
C. 40
D. 50
Answer» D. 50