| 1. |
2 employees and 3 trainees together can finish a project in 7 days, 6 employees and 13 trainees together can finish the same project in 2 days. Find the time taken by 4 employees and 4 trainees together to finish the same work. |
| A. | 4 days |
| B. | 5 days |
| C. | 6 days |
| D. | 8 days |
| E. | None of these |
| Answer» B. 5 days | |