1. |
16 workers working 8 hours per day can demolish a building in 32 days. In how many days 24 workers working 12 hours per day can demolish the same building? |
A. | 128/3 days |
B. | 56/3 days |
C. | 128/9 days |
D. | 56/9 days |
Answer» D. 56/9 days | |