1. |
16 men complete a work in 20 days. After they have worked for 12 days, 8 more men join them. How many days will they take to complete the remaining work? |
A. | 14/3 days |
B. | 16/3 days |
C. | 8/3 days |
D. | 6 days |
Answer» C. 8/3 days | |