1.

16 children and 24 men complete a certain work for 18 days. If each child takes twice the time taken by a man to finish the work in how many days will 24 men finish the same work ?

A. 12 days
B. 24 days
C. 36 days
D. 48 dyas
E. None of the above
Answer» C. 36 days