12 men can do a piece of work in 16 days. After six days three more men join them. Then in how many days will the remaining work be finished?( ADP COMPANY) |
A. | 8 days |
B. | 14 days |
C. | 12 days |
D. | 10 days |
Answer» B. 14 days | |