1. |
1/3 part of a work can be completed in 8 days by 30 men. How many more men will be required to finish the rest in the next 10 days?A. 10B. 18C. 12D. 9 |
A. | A |
B. | B |
C. | C |
D. | D |
Answer» C. C | |